New South Wales mining projects: what's being built, funded and restarted
55 mining projects in New South Wales are on our development and restart pipeline: 16 study, 9 official list only (not refreshed), 7 stage not established, 5 under construction. Each was checked against 2026 company reports and regulator pages where defensible evidence exists; the rest show the official October 2025 list.
By stage
By commodity
Coming up in New South Wales
- Port Kembla Blast Furnace Reline
late 2026 · Under construction - Cowal Open Pit Continuation Project
June 2026 quarter · Under construction - Moolarben Coal Complex OC3 Extension Project
2027 · Study - Tomingley Gold Operations - Newell Highway realignment and open pit mining (San Antonio)
early June 2027 quarter · Under construction - Tallebung Tin Project
mid-2028 · Study - Great cobar (Peak expansion)
FY28 · Under construction - Dubbo Project (Toongi rare earths, zirconium, niobium, hafnium)
30 Jun 2029 · Approved, not funded
In the news
- NSW Passes Bill to Keep Mount Pleasant Mine Running to 2032
discoveryalert.com · 2026-11-20 · Mount Pleasant Optimisation Project - Four Bowdens Silver motions pass despite staff advice against further action
Mudgee Guardian · 2026-11-19 · Bowdens Project - Sunrise Energy Metals clears FIRB hurdle for Nasdaq move
Grafa · 2026-11-18 · Sunrise Project - Larvotto bags US$30M prepayment to fuel NSW gold-antimony ramp-up
The Sydney Morning Herald · 2026-11-18 · Hillgrove Gold-Antimony Project - Aeris Resources (ASX:AIS): Tritton Production and Constellation Development
kalkine · 2026-11-18 · Constellation Project - Kingston Hits 18.5m at 7.63% Copper Equivalent in Mineral Hill Drilling
discoveryalert.com · 2026-11-17 · Mineral Hill
| Project | State | Commodity | Stage | As at |
|---|---|---|---|---|
| Abel | NSW | Coal | Official list only (not refreshed) | Oct 2025 |
| Balranald Project | NSW | Rare earths | Commissioning / ramp-up | 2026-07 |
| Boggabri Coal Extension | NSW | Coal | Stage not established | Oct 2025 |
| Bowdens Project | NSW | Zinc, lead & silver | Study | 2026-07 |
| Bulga Optimisation Project mod 3 and Bulga Underground mod 7 | NSW | Coal | Official list only (not refreshed) | Oct 2025 |
| Burra project | NSW | Scandium | Official list only (not refreshed) | Oct 2025 |
| Bushranger | NSW | Copper | Official list only (not refreshed) | Oct 2025 |
| Cadia copper and gold and it's tailing storage extension | NSW | Copper | Official list only (not refreshed) | Oct 2025 |
| Chain Valley Extension | NSW | Coal | Stage not established | Oct 2025 |
| Constellation Project | NSW | Copper | Under construction | 2026-10 |
| Copi Project | NSW | Mineral sands | Approved, not funded | 2026-05 |
| Copper Hill project | NSW | Copper | Study | 2026-06 |
| Cowal Open Pit Continuation Project | NSW | Gold | Under construction | 2026-09 |
| Cullen Valley | NSW | Coal | Stage not established | Oct 2025 |
| Dartbrook Mine extension | NSW | Coal | On hold / care and maintenance | 2026-08 |
| Dubbo Project (Toongi rare earths, zirconium, niobium, hafnium) | NSW | Rare earths | Approved, not funded | 2026-11 |
| Endeavor Mine restart | NSW | Zinc, lead & silver | Producing | 2026-06 |
| Euston Mineral sands | NSW | Rare earths | Official list only (not refreshed) | Oct 2025 |
| Flemington Scandium Project | NSW | Scandium | Study | 2026-09 |
| Great cobar (Peak expansion) | NSW | Copper | Under construction | 2026-08 |
| Hawsons Iron Project | NSW | Iron Ore | Study | 2026-07 |
| Hera | NSW | Copper | Official list only (not refreshed) | Oct 2025 |
| Hillgrove Gold-Antimony Project | NSW | Antimony | Commissioning / ramp-up | 2026-09 |
| Hunter Valley Operations Continuation Project | NSW | Coal | Producing | 2026-09 |
| Mallee Bull (South Cobar Copper) | NSW | Copper | Study | 2026-07 |
| Maules Creek Continuation Project | NSW | Coal | Study | 2026-02 |
| Maxwell Underground Mine | NSW | Coal | Producing | 2026-07 |
| McPhillamys | NSW | Gold | Study | 2026-10 |
| Metropolitan Continuation Project | NSW | Coal | Study | 2026-09 |
| Mineral Hill | NSW | Gold | On hold / care and maintenance | 2026-06 |
| Moolarben CHPP upgrade | NSW | Coal | Official list only (not refreshed) | Oct 2025 |
| Moolarben Coal Complex OC3 Extension Project | NSW | Coal | Study | 2026-06 |
| Mount Pleasant Optimisation Project | NSW | Coal | Study | 2026-11 |
| Mt Carrington Gold-Silver Project | NSW | Gold | Study | 2026-09 |
| Mt Thorley | NSW | Coal | Study | 2026-10 |
| Narrabri (Stage 3) | NSW | Coal | Official list only (not refreshed) | Oct 2025 |
| New Occidental Tailings Retreatment | NSW | Gold | Study | 2026-06 |
| Newstan Mine Extension | NSW | Coal | Stage not established | Oct 2025 |
| Northparkes E22 Block Cave | NSW | Gold | Funded, FID taken | 2026-08 |
| Nyngan Scandium Project | NSW | Scandium | Approved, not funded | 2026-10 |
| Pine Dale | NSW | Coal | On hold / care and maintenance | 2026-03 |
| Pinnacles Mine restart (feeding Rasp Processing Plant) | NSW | Zinc, lead & silver | Stage not established | Oct 2025 |
| Port Kembla Blast Furnace Reline | NSW | Iron Ore | Under construction | 2026-08 |
| Rix's Creek North Continuation Project | NSW | Coal | Study | 2026-10 |
| Sunrise Project | NSW | Nickel & cobalt | On hold / care and maintenance | 2026-10 |
| Syerston Scandium Project | NSW | Scandium | Funded, FID taken | 2026-11 |
| Tahmoor Mine restart | NSW | Coal | Restart planned | 2026-10 |
| Tallebung Tin Project | NSW | Tin | Study | 2026-08 |
| Taronga Tin Project | NSW | Tin | Stage not established | Oct 2025 |
| Tomingley Gold Operations - Newell Highway realignment and open pit mining (San Antonio) | NSW | Gold | Under construction | 2026-09 |
| Vickery | NSW | Coal | Approved, not funded | 2026-09 |
| Wallarah 2 | NSW | Coal | Stage not established | Oct 2025 |
| Wilpinjong Continuation Project (Pits 9 and 10) | NSW | Coal | Study | 2026-06 |
| Wonawinta Silver-Gold Project restart | NSW | Gold | Commissioning / ramp-up | 2026-08 |
| Woodlawn copper-zinc mine restart | NSW | Copper | Producing | 2026-06 |
For these 55 projects the dataset holds 39 current stages, 19 target first-production dates, 13 capital cost figures, 11 named contractor entries, 29 approval statuses and 11 funding details, each with a source link and as-at date. Blank means we could not support a figure with a checked source.
Development & Restart Pipeline: 453 projects with stage, target first production, capital cost, named contractors, approvals and funding, each with a source link and as-at date, plus an interactive map. A$299.
Or the bundle with the Verified Edition (who owns 346 mine sites): A$449. One-time purchase, CSV + map + README.
See pricingFree 10-row sampleFree map previewBrowse the pipeline
By state: Western Australia · Queensland · New South Wales · South Australia · Northern Territory · Victoria · Tasmania
By stage: Building now · Waiting on funding · Restarts · Stalled or withdrawn · Still in study · What moved since the official list
By commodity: Gold · Coal · Iron Ore · Copper · Other · Nickel & cobalt · Rare earths · Lithium · Zinc, lead & silver · Mineral sands · Bauxite & alumina · Graphite · Vanadium · Phosphate & potash · Uranium · Tin · Manganese · High-purity silica · Kaolin · Scandium · Salt