Balranald Project
As at 22 November 2026, our dataset places Balranald Project (Iluka Resources) in NSW at the stage Commissioning / ramp-up (evidence dated 2026-07): the plant is built and ramping up. The target we hold is June 2026 (first production), as stated by the company and dated 2026-07.
Compare with other projects My watchlist (saved in this browser only)
| Proponent | Iluka Resources |
|---|---|
| State | NSW |
| Commodity | Ilmenite, zircon, rutile, mixed rare earth concentrate |
| Type | New project |
| Stage | Commissioning / ramp-up (as at 2026-07) |
| Target date | June 2026 (first production) |
| Official list (Oct 2025) | Committed |
| Official capital cost (Oct 2025) | A$480m |
| Official start year (Oct 2025) | 2025 |
In the news
No recent headlines found for this project (checked 2026-11-21).
Where to go next
- Department of Industry Australian Industry Participation plan summary (Approved, published 11/09/2023): usually names work packages and contractors.
What the dataset holds for this project
Capital cost – · named contractors – · approvals – · funding – · first-production target ✓. Each fact has a source link, a quoted passage and an as-at date. A dash means no sourced figure yet.
Development & Restart Pipeline: every project with stage, capital cost, named contractors, approvals and funding, each with a source link and as-at date, plus an interactive map. A$299.
See pricingFree 10-row sampleFree map previewOnly need NSW, SA, NT, VIC and TAS? Every project there as a separate file: A$149 (or the full pipeline, A$299).
Related projects
- Copi Project (Approved, not funded)
- Hillgrove Gold-Antimony Project (Commissioning / ramp-up)
- Nyngan Scandium Project (Approved, not funded)
- Taronga Tin Project (Stage not established)
- Dubbo Project (Toongi rare earths, zirconium, niobium, hafnium) (Approved, not funded)
- Tallebung Tin Project (Study)