Western Ridge
As at 22 November 2026, our dataset places Western Ridge (BHP/ITOCHU/Mitsui) in WA at the stage Under construction (evidence dated 2026-09): construction is under way. The target we hold is H1 FY2026-27 (first ore, targeted), as stated by the company and dated 2026-09.
Compare with other projects My watchlist (saved in this browser only)
| Proponent | BHP/ITOCHU/Mitsui |
|---|---|
| State | WA |
| Commodity | Hematite |
| Type | Expansion |
| Stage | Under construction (as at 2026-09) |
| Target date | H1 FY2026-27 (first ore) |
| Official list (Oct 2025) | Committed |
| Official capital cost (Oct 2025) | A$1400m |
| Official start year (Oct 2025) | 2026 |
In the news
No recent headlines found for this project (checked 2026-11-21).
Where to go next
- Department of Industry Australian Industry Participation plan summary (Approved, published 09/06/2021): usually names work packages and contractors.
What the dataset holds for this project
Capital cost – · named contractors – · approvals – · funding – · first-production target ✓. Each fact has a source link, a quoted passage and an as-at date. A dash means no sourced figure yet.
Development & Restart Pipeline: every project with stage, capital cost, named contractors, approvals and funding, each with a source link and as-at date, plus an interactive map. A$299.
See pricingFree 10-row sampleFree map previewOnly need Western Australia? Every project there as a separate file: A$199 (or the full pipeline, A$299).
Related projects
- Christmas Creek Green Iron Metal Project (Commissioning / ramp-up)
- Lake Giles iron ore project (Moonshine and Ularring) (Study)
- Ridley Magnetite Project (Stage not established)
- Robe Mesa (Stage not established)
- West Angelas Sustaining Project (Under construction)
- Brockman Syncline 1 (Under construction)