Mt Bundy
As at 22 November 2026, our dataset places Mt Bundy (Primary Gold Pty Ltd (Hanking Australia Investment)) in NT at the stage Under construction (evidence dated 2026-08): construction is under way. The target we hold is Q1 2028 (first production, targeted), as stated by the company and dated 2026-08.
Compare with other projects My watchlist (saved in this browser only)
| Proponent | Primary Gold Pty Ltd (Hanking Australia Investment) |
|---|---|
| State | NT |
| Commodity | Gold |
| Type | Reactivation |
| Stage | Under construction (as at 2026-08) |
| Target date | Q1 2028 (first production) |
| Official list (Oct 2025) | Advanced feasibility |
| Official capital cost (Oct 2025) | A$412m |
| Official start year (Oct 2025) | 2025+ |
In the news
No recent headlines found for this project (checked 2026-11-21).
Where to go next
What the dataset holds for this project
Capital cost – · named contractors ✓ · approvals ✓ · funding – · first-production target ✓. Each fact has a source link, a quoted passage and an as-at date. A dash means no sourced figure yet.
Development & Restart Pipeline: every project with stage, capital cost, named contractors, approvals and funding, each with a source link and as-at date, plus an interactive map. A$299.
See pricingFree 10-row sampleFree map previewOnly need NSW, SA, NT, VIC and TAS? Every project there as a separate file: A$149 (or the full pipeline, A$299).
Related projects
- Tanami Expansion 2 (Under construction)
- Mt Todd (Approved, not funded)
- Tennant Creek Copper Project (Orlando) (Study)
- Twin Bonanza Restart Project (Old Pirate Gold Mine) (Study)
- White Devil Gold Project (Tennant Creek) (Commissioning / ramp-up)