Mining · November 2026

What the official list of Australian mining projects hasn't caught up with

The federal Resources and Energy Major Projects list (Office of the Chief Economist, October 2025) names 111 mining and processing projects that are Committed (46) or in Advanced feasibility (65). We checked each one against company reports and regulator pages dated 2026. Every fact we publish has a source link and a quoted passage.

Where the 111 stand today

PositionProjects
No defensible 2026 evidence38
Funded or being built35
Still in study19
Approved but not funded12
Now producing or completed4
Stalled or withdrawn2
Restart planned1

Three projects that moved

Kangwinan (Rio Tinto, Queensland bauxite). The official list shows Advanced feasibility and A$200m. Rio Tinto approved the investment on 23 October 2026: a US$1.9 billion capital estimate (including early works), first output targeted for 2029 and full production by 2032 (source).

Yitirrti, formerly Sulphur Springs (Develop Global, WA copper-zinc). The official list shows Advanced feasibility and A$329m. It is now under construction (source), with a A$450m total capital cost estimate (source) and a A$275m EPC contract awarded to GR Engineering Services (source).

Vickery (Whitehaven, NSW coal). Listed as Committed. In its September 2026 quarterly the company says the full-scale development has all required government approvals but remains subject to a Board final investment decision (source).

Not every project is moving

Mackay Potash (Agrimin, WA). The official list shows Advanced feasibility and A$620m. Agrimin's June 2026 quarterly report indicates the company is withdrawing from the project (source). Sunrise Project (Sunrise Energy Metals). Listed at A$2.7bn; the company's October 2026 quarterly report says activity at the nickel-cobalt sulphate complex is focused on minimising holding costs until market conditions improve (source). Great White Kaolin Project (Andromeda, SA). Listed as Committed; as at mid-2026 it has no final investment decision and still needs a balance of equity funding (source).

The 38 we could not confirm

For 38 of the 111 we found no 2026 evidence we could verify, so we do not assert a stage for them. That does not mean they have stalled: many are privately held or report rarely. Treat the official-list entry for these as unconfirmed.

The full breakdown, with every project listed by state, commodity and stage, is free at what moved since the official list.

Development & Restart Pipeline: 453 projects with stage, target first production, capital cost, named contractors, approvals and funding, each with a source link and as-at date, plus an interactive map. A$299.

Or the bundle with the Verified Edition (who owns 346 mine sites) and a company view: A$449. One-time purchase.

See pricingFree 10-row sampleFree map preview